For covered procurement above the relevant thresholds, the GWB provides a specialised review system. A bidder must establish its interest, the alleged violation of its procurement rights and actual or threatened harm. A complaint to the authority and a review application are different procedural steps.
Practical implications
Section 134 GWB generally requires a standstill of 15 calendar days after dispatch of award information, reduced to ten for electronic or fax transmission. Exceptions apply. Do not confuse that standstill with the complaint or review-application deadlines. The exact communication, sending method and chronology matter.
Three practical examples
1. An intended-award notice arrives electronically
The bidder preserves the full message and receipt details and calculates the applicable standstill and objection timetable separately. It reviews the reasons immediately. Waiting until the last day of one period can be unsafe if another requirement expires earlier or if the notice raises a different procedural issue.
2. A restrictive condition is apparent in the documents
A bidder sees an excessive qualification requirement before the submission deadline. It should assess and raise the issue at that stage, rather than waiting to be excluded. The legal review considers the applicable preclusion rule and the evidence showing how the condition affects participation.
3. The buyer rejects the complaint
The response is added to the deadline chronology and assessed for its procedural consequences. The bidder decides promptly whether to seek formal review and interim protection. Continuing an informal exchange should not be assumed to preserve a statutory filing period or prevent the authority from awarding the contract.
Explore our procurement services · Read current insights and the archive
Legal reference: Official source. Reviewed 12 November 2026. This overview does not replace advice on the relevant procurement and its deadlines.
Identify the protective window
Read the proposed-award notice immediately and preserve evidence of receipt. Establish the applicable waiting period and the separate time limits for raising and pursuing objections. Do not assume that every message from the authority starts the same clock or that a clarification request amounts to a formal complaint.
Coordinate substance and procedure
State the alleged defect and its effect on the bidder’s chances with enough specificity to permit correction. Assess the need for a review application before award can occur. The application, costs, evidence and possible outcomes should be considered together rather than treating filing as an automatic next step.
A practical working sequence
- Record receipt and the intended award date.
- Separate complaint requirements from review deadlines.
- Assess the evidence and remedy before signature.
Documents, decisions and next steps
For an urgent assessment, provide a dated chronology and the complete notices, tender documents and correspondence. Explain the commercial objective and whether the contract has already been signed. We distinguish the legal merits from admissibility, timing, interim protection and the practical result a proceeding could achieve. The authority’s response may resolve one issue while leaving another open, so the position should be reassessed at each material step. Keep original electronic messages and attachments, rather than relying only on a summary of a telephone conversation. Any proposed settlement should be checked for its effect on the procurement and on the other participants.
German state rules · EU country guides · Special procedures · Industry guidance
Discuss your procurement
Tell us whether you are a bidder or contracting authority, identify the procurement and include the next deadline. We assess the scope, conflicts and proposed next steps before accepting instructions.